ProjectBank

  • 40MW Solar Thermal Station

    Power Tower
    • Project Category: Energy, Environment
    • Company: Abengoa Hellas Solar Ltd.
    • Region: Sitia, Crete
    • Year: 2010
    • Status: Under Licensing
    • Our contribution: Land Hunting and securing the land, Topographic Survey, Production License, Environmental Impact Assessment, Installation License

    One of the largest approved RES project is Crete is developed by Entec Consultants on behalf of the listed multinational Spanish company Abengoa SA

  • 22,6MW Wind Farms

    Αιολικό Πάρκο
    • Project Category: Energy, Enterprise
    • Company: Hellenic Postbank
    • Region: Lesvos, Kefalonia
    • Year: 2011
    • Status: In operation
    • Our contribution: Technical Due Diligence

    Entec Consultants conducted a thorough technical due diligence for the refinancing of three operational wind farms in Greek islands.

  • 1GW Photovoltaic Stations

    PV Project
    • Project Category: Energy
    • Company: Pancreta Renewables S.A.
    • Region: Crete
    • Year: 2012
    • Status: Under Licensing
    • Our contribution: Land hunting, Topographic Survey, Production License

    Licensing of the strategically important Pancreta Renewables S.A. project and especially the Eastern Crete part was assigned to Entec Consultants. The project is supported by a underwater HVDC connection line to the mainland that secures the supply of clean power and the safe operation of the island's electrical system.

  • 25MW Solar Thermal Stations

    Stirling Dish
    • Project Category: Energy
    • Company: CSP Dish Systems Ltd + 18 other SPVs
    • Region: Crete & Rhodes
    • Year: 2011
    • Status: Under Licensing
    • Our contribution: Land hunting, System design & modeling, Production License

    The first 19 Dish-Stirling type Solar Thermal Stations in Crete and Rhodes, totaling a 25,1MW of power, are developed by Entec Consultants. Except from greenfield development, company also developed and energy simulation model and user interface for the modeling of the systems according to the strict operational requirements in the Greek Non-Interconnected Islands.

  • 6,13MW Photovoltaic Stations

    PV Project
    • Project Category: Energy, Environment
    • Company: Capital Renewables S.A.
    • Region: Thina, Argolida
    • Year: 2007
    • Status: In Operation
    • Our contribution: Land Hunting, Topographic Survey, Production License, Environmental Impact Assessment, Installation License, Operation License

    A 4,13 MW PV station in Argolida and a 2,0MW in Thiva were "turnkey" developed by Entec Consultants for Capital Renewables SA. Capital Renewables is member of the NASDAQ-listed group "Capital Product Partners L.P."

  • Sisi-Milatos Beach Reformation

    Παραλιακό μέτωπο
    • Project Category: Environment
    • Company: Aghios Nikolaos Municipality
    • Region: Sissi and Milatos, Lassithi
    • Year: 2011
    • Status: Delivered
    • Our Contribution: Environmental Impact Assessment, Renewable Energy Sustainability Study

    We investigated environmental conditions on the coastal areas of Sissi and Milatos villages and proposed solutions for the protection and restoration of the environment and the sustainable integration of renewable energy sources.

  • 40MW Wind Farm

    Αιολικό Πάρκο
    • Project Category: Energy, Environment
    • Company: Bright Wind and Solar Ltd.
    • Region: Petritsi, Serres
    • Year: 2011
    • Status: Under Licensing
    • Our contribution: Construction and certification of a 30m wind measuring station, Production License, Environmental Impact Assessment
  • 150 Photovoltaic Stations in Crete, 80kW each

    PV Project
    • Project category: Energy, Enterprise, Environment
    • Company: More than 100 SPVs
    • Region: Crete
    • Year: 2007
    • Status: In operation
    • Our Contribution: Greenfield development, Production license exempt, Environmental impact assessment, Building permit, Development law subsidy

    More than 150 PV stations currently owned and operated by more than 100 enterprises were turn-key developed by Entec Consultants including their complete licensing procedures as well as 40% subsidy from the Development Law N.3299/2004.

  • Medical Waste Treatment

    Ιατρικά Απόβλητα
    • Project Category: Environment
    • Company: Medical Waste S.A.
    • Region: Heraklion Industrial Area
    • Year: 2009
    • Status: Completed
    • Our contribution: Environmental Impact Assessment

    A very complicate and demanding Environmental Impact Assessment study and authorization was conducted for the Greek innovative firm "Medical Waste S.A.". Licensing was completed in a record timeframe of three (3) months.

  • Kidney Dialysis Center

    Mesogeios
    • Project Category: Energy, Environment
    • Company: Mesogeios Dialysis Center S.A.
    • Region: Heraklion
    • Year: 2008
    • Status: Completed
    • Our contribution: Environmental Impact Assessment, Waste Water Treatment, Energy Saving, 80kW Grid Connected PV System

    Our company offers complete and integrated environmental services to the widely acknowledged "Mesogeios" Kindey Dialysis Center in Kalessa, Heraklion, Crete

  • Food & Drinks Trade Center

    Makro
    • Project Category: Environment
    • Company: Macro Cash & Carry
    • Region: Heraklion
    • Year: 2011
    • Status: Completed
    • Our Contribution: Environmental Impact Assessment

    A very demanding Environmental Impact Assessment study for Crete's largest food and drink wholesale supplier was conducted by Entec Consultants.

Contact